PROGRESS AT OLIVIA


M A Y 2 0 2 5


Storm shelter is ready for a concrete pour, which will be placed over the steel rebar and yellow vapor barrier to form a strong, durable slab floor.

Work inside the building continues as drywall, lighting, and painting in district office wraps up and flooring work begins. Demolition work in high school and elementary wing is also getting started.


M A R C H 2 0 2 5


Foundation walls and footings for the Strom Shelter were completed this month.

Work inside the building has begun with demolition of district office complete and steel studs and rough-ins underway.


F E B R U A R Y 2 0 2 5


Exterior pool work is complete, and interior work is 95% finished with tile work coming in March.

Work on new sanitary piping has begun.

Storm shelter work was paused due to extreme cold — days like these required frost blankets to be laid out.


D E C E M B E R 2 0 2 4


Exterior Pool Wall Restoration is 89% Complete, and interior wall demo has begun

Storm shelter fencing/removals underway and footing excavation/pouring begins in January

Utility relocation has begun


S E P T E M B E R 2 0 2 4


New field lighting is installed

Playground is complete with new gaga ball pit and four square

New playground equipment and swings are installed

New track is also 100% complete