PROGRESS AT OLIVIA
J U L Y 2 0 2 5
Mechanical room roof and the main office corridor are being removed to prepare for the new main entrance construction at the Olivia building.
Interior painting, flooring and lighting finishes are wrapping up in the storm shelter and flooring installation is next.
Roofing parapet is being added between storm shelter and existing pool building roof at Olivia.
Cutouts of the exterior wall are prepared for new mechanical system installations.
The old district office was transformed into new classrooms (including a Science Room) and is close to completion.
Work inside the building continues as elementary breakout spaces take shape.
Water service is compete for the new Storm Shelter.
M A Y 2 0 2 5
Storm shelter is ready for a concrete pour, which will be placed over the steel rebar and yellow vapor barrier to form a strong, durable slab floor.
Work inside the building continues as drywall, lighting, and painting in district office wraps up and flooring work begins. Demolition work in high school and elementary wing is also getting started.
M A R C H 2 0 2 5
Foundation walls and footings for the Strom Shelter were completed this month.
Work inside the building has begun with demolition of district office complete and steel studs and rough-ins underway.
F E B R U A R Y 2 0 2 5
Exterior pool work is complete, and interior work is 95% finished with tile work coming in March.
Work on new sanitary piping has begun.
Storm shelter work was paused due to extreme cold — days like these required frost blankets to be laid out.
D E C E M B E R 2 0 2 4
Exterior Pool Wall Restoration is 89% Complete, and interior wall demo has begun
Storm shelter fencing/removals underway and footing excavation/pouring begins in January
Utility relocation has begun
S E P T E M B E R 2 0 2 4
New field lighting is installed
Playground is complete with new gaga ball pit and four square
New playground equipment and swings are installed
New track is also 100% complete