PROGRESS AT OLIVIA
M A R C H 2 0 2 5
Foundation walls and footings for the Strom Shelter were completed this month.
Work inside the building has begun with demolition of district office complete and steel studs and rough-ins underway.
F E B R U A R Y 2 0 2 5
Exterior pool work is complete, and interior work is 95% finished with tile work coming in March.
Work on new sanitary piping has begun.
Storm shelter work was paused due to extreme cold — days like these required frost blankets to be laid out.
D E C E M B E R 2 0 2 4
Exterior Pool Wall Restoration is 89% Complete, and interior wall demo has begun
Storm shelter fencing/removals underway and footing excavation/pouring begins in January
Utility relocation has begun
S E P T E M B E R 2 0 2 4
New field lighting is installed
Playground is complete with new gaga ball pit and four square
New playground equipment and swings are installed
New track is also 100% complete