PROGRESS AT BIRD ISLAND
M A Y 2 0 2 5
Work on the West end of the building — which includes locker rooms, offices, and changing room — continues as planned. Mechanical inspections passed, concrete is poured and work is underway installing steel stud walls and mechanical/electrical rough ins. Drywall is expected to begin in June.
M A R C H 2 0 2 5
Interior demolition is nearing completion and abatement work at West end of school is complete.
F E B R U A R Y 2 0 2 5
Removal of ceiling tiles and casework is underway as part of interior demolition phase.
Floor protection has been installed to prep for interior demolition.
DECEMBER 2 0 2 4
Gym Seating 98% Complete
Gym Flooring 98% Complete
Stage Curtains 85% Complete